1. 3-Plant to 4-Warehouse Distribution
Logistics AnalystBackground
A manufacturing company operates three production plants with capacities 30, 40, and 30 units, delivering to four regional warehouses requiring 20, 30, 30, and 20 units.
Problem
Determine the lowest-cost shipping schedule across 12 candidate routes with variable unit transit rates.
How to use
Input the 3x4 rate matrix into Costs, set Supply to '30, 40, 30', Demand to '20, 30, 30, 20', and leave Decimal Places at 4.
Costs:
2, 3, 1, 4
4, 2, 5, 3
3, 1, 4, 2
Supply: 30, 40, 30
Demand: 20, 30, 30, 20Outcome
Finds the global minimum total freight cost of 200 with an exact routing plan and MODI dual potentials confirming optimality.